Concrete calculation program and costs for all concrete elements

 

 

Concrete calculation program and costs for all concrete elements


How to calculate concrete and rebar in an approximate and fast way, until accurate designs are made

Examples

First: the regular ceiling (Solid Slab)

2- Ceiling area = 200 square meters

3- Amount of concrete = roof thickness x roof area

4- The amount of concrete = 0.15 x 200

5- The amount of concrete = 30 cubic meters

6- The amount of iron = 80 / 100 kg / cubic meter

7- The amount of iron = 80 x 30

8- The amount of iron = 2400 kilograms

9- The amount of iron = 2.40 tons

  Second: the cameras

1- The amount of concrete = 1/3 the amount of ceiling concrete 2- The amount of concrete = 1/3 x 30 3- The amount of concrete = 10 cubic meters 4- The amount of iron = 60 / 70 kg / cubic meter 5- The amount of iron = 60 x 10 6 - Amount of iron = 600 kilograms 7 - Amount of iron = 0.60 tons Total amount of iron = Amount of iron (roof) + Amount of iron (beams) Amount of iron = 2.40 + 0.60 Amount of iron = 3 tons Amount of concrete = Amount of concrete (ceiling) + Amount Concrete (beams) The amount of concrete = 30 + 10 The amount of concrete = 40 cubic meters